Which is the tool or technique that is used to obtain the list of activities from the work packages?

A.
Data analysis
Answers
A.
Data analysis
B.
Leads and lags
Answers
B.
Leads and lags
C.
Precedence diagramming method
Answers
C.
Precedence diagramming method
D.
Decomposition
Answers
D.
Decomposition
Suggested answer: D