A project manager is identifying the risks of a project. Which technique should the project manager use?

A.
Representations of uncertainty
Answers
A.
Representations of uncertainty
B.
Prompt lists
Answers
B.
Prompt lists
C.
Audits
Answers
C.
Audits
D.
Risk categorization
Answers
D.
Risk categorization
Suggested answer: B