Which components of the project management plan are inputs used when creating the stakeholder engagement plan?

A.
Risk, resource, and communications management plans
Answers
A.
Risk, resource, and communications management plans
B.
Scope, quality, and resource management plans
Answers
B.
Scope, quality, and resource management plans
C.
Procurement, integration, and risk management plans
Answers
C.
Procurement, integration, and risk management plans
D.
Communications, schedule, and cost management plans
Answers
D.
Communications, schedule, and cost management plans
Suggested answer: A