A project manager Is in the process of working with stakeholders to meet their needs and expectations, and identifying and fostering communication and involvement. Which process does this typically represent?

A.
Monitor Stakeholder Engagement
Answers
A.
Monitor Stakeholder Engagement
B.
Monitor Communications
Answers
B.
Monitor Communications
C.
Manage Communications
Answers
C.
Manage Communications
D.
Manage Stakeholder Engagement
Answers
D.
Manage Stakeholder Engagement
Suggested answer: D