The project management plan requires the acquisition of a special part available from a supplier located abroad. Which source selection method is being used?

A.
Least cost
Answers
A.
Least cost
B.
Qualifications only
Answers
B.
Qualifications only
C.
Sole source
Answers
C.
Sole source
D.
Fixed budget
Answers
D.
Fixed budget
Suggested answer: B