A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

A.
Informal communication
Answers
A.
Informal communication
B.
Internal communication
Answers
B.
Internal communication
C.
Formal communication
Answers
C.
Formal communication
D.
Horizontal communication
Answers
D.
Horizontal communication
Suggested answer: C