What are the inputs of the Estimate Costs process?
A.
Project management plan, work performance data, enterprise environmental factors, and organizational process assets
B.
Project management plan, project documents, enterprise environmental factors, and organizational process assets
C.
Cost baseline, enterprise environmental factors, benefits management plan, and organizational process assets
D.
Project management plan, enterprise environmental factors, basis of estimates, and organizational process assets