Question 859 - CAPM discussion
At the beginning of an iteration, the team will work to determine how many of the highest-priority items on the backlog list can be delivered within the next iteration. Which of the following activities is done first?
A.
Create Work Breakdown Structure (WBS)
B.
Create Scope Baseline
C.
Collect Requirements
D.
Define Scope
Your answer: