A project manager is formalizing acceptance of the completed project deliverables. What is an input to this process?

A.
Verified deliverables
Answers
A.
Verified deliverables
B.
Validated deliverables
Answers
B.
Validated deliverables
C.
Accepted deliverables
Answers
C.
Accepted deliverables
D.
Completed change requests
Answers
D.
Completed change requests
Suggested answer: A