A new project has been set. Four main stakeholders besides the project manager and four other team members have been identified. How many communication channels are available?

A.
8
Answers
A.
8
B.
18
Answers
B.
18
C.
36
Answers
C.
36
D.
40
Answers
D.
40
Suggested answer: C