Question 892 - CAPM discussion

Report
Export

What is the difference between verified and accepted deliverables?

A.
Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.
Answers
A.
Accepted deliverables have been completed and checked for correctness; verified deliverables have been formally approved by the customer or authorized stakeholder.
B.
Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.
Answers
B.
Accepted deliverables have been inspected by the quality team; verified deliverables are outputs from the Validate Scope process.
C.
Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.
Answers
C.
Accepted deliverables have been formally signed off and approved by the authorized stakeholder; verified deliverables have been completed and checked for correctness.
D.
Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.
Answers
D.
Accepted deliverables have been formally accepted by the project manager; verified deliverables are the outputs from the Control Quality process.
Suggested answer: D