Why is tailoring in a project necessary?

A.
Requirements keep changing.
Answers
A.
Requirements keep changing.
B.
An artifact must be produced.
Answers
B.
An artifact must be produced.
C.
A tool or technique is required.
Answers
C.
A tool or technique is required.
D.
Each project is unique.
Answers
D.
Each project is unique.
Suggested answer: D

Explanation:

Each project is unique, and the members of the project team should select the appropriate tools, techniques, inputs, and outputs from the PMBOK Guide.