In a functional organization, the director of an important stakeholder business group expressed concern to a line manager about the progress of the project. What should the line manager do next?

A.
Hold a face-to-face meeting with the project manager and warn them.
Answers
A.
Hold a face-to-face meeting with the project manager and warn them.
B.
Point the director to a link where they can take a look at the reports.
Answers
B.
Point the director to a link where they can take a look at the reports.
C.
Invite stakeholders to attend monthly progress review meetings.
Answers
C.
Invite stakeholders to attend monthly progress review meetings.
D.
Ask the project manager to update the monthly status report distribution list.
Answers
D.
Ask the project manager to update the monthly status report distribution list.
Suggested answer: C