Which is a key objective of running a workshop?

A.
To make daily progress visible to the delivery team and key stakeholders
Answers
A.
To make daily progress visible to the delivery team and key stakeholders
B.
To encourage collaboration and create the defined outputs from the event
Answers
B.
To encourage collaboration and create the defined outputs from the event
C.
To communicate decisions to the wider stakeholder community
Answers
C.
To communicate decisions to the wider stakeholder community
D.
To make day-to-day decisions on behalf of the delivery team within a sprint
Answers
D.
To make day-to-day decisions on behalf of the delivery team within a sprint
Suggested answer: B

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_166&showNav=true&expandNav=true