ExamGecko
Home / PRINCE2 / PRINCE2 Agile Foundation / List of questions
Ask Question

PRINCE2 PRINCE2 Agile Foundation Practice Test - Questions Answers, Page 3

List of questions

Question 21

Report
Export
Collapse

Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

It reduces testing in order to meet deadlines
It reduces testing in order to meet deadlines
It sets the project baseline at the correct level
It sets the project baseline at the correct level
It enables team dynamics to remain the same
It enables team dynamics to remain the same
It improves the supplier's reputation with the customer
It improves the supplier's reputation with the customer
Suggested answer: A

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41

asked 23/09/2024
Carlos Cabezas
49 questions

Question 22

Report
Export
Collapse

Which statement about the ‘protect the level of quality’ target is CORRECT?

It is achieved by allowing enough time for testing
It is achieved by allowing enough time for testing
It is achieved by using the same team members
It is achieved by using the same team members
It gives confidence on the progress of the project
It gives confidence on the progress of the project
It delivers the early realization of benefits
It delivers the early realization of benefits
Suggested answer: D

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41#:~:text=PRINCE2%20Agile%20protects%20the%20level,the%20quality%20level%20is%20met

asked 23/09/2024
Miroslav Vukic
37 questions

Question 23

Report
Export
Collapse

Which statement describes the Kanban approach?

It is used to make system improvements using visualization and by controlling work in progress
It is used to make system improvements using visualization and by controlling work in progress
It is an iterative timeboxed approach that helps teams generate value
It is an iterative timeboxed approach that helps teams generate value
It was originally focused in creating new companies and is now used to speed up product delivery
It was originally focused in creating new companies and is now used to speed up product delivery
It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
Suggested answer: A

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_244

asked 23/09/2024
Katrina Allangba
40 questions

Question 24

Report
Export
Collapse

What information is NOT typically displayed on a burn chart?

Effort remaining
Effort remaining
Team working agreements
Team working agreements
Actual amount of work done
Actual amount of work done
Amount of time elapsed
Amount of time elapsed
Suggested answer: B
asked 23/09/2024
Maxim Shpakov
41 questions

Question 25

Report
Export
Collapse

In which area is Agile strongest when blending with PRINCE2?

Product delivery
Product delivery
Project management
Project management
Project direction
Project direction
Product management
Product management
Suggested answer: A

Explanation:

Reference: https://hennyportman.wordpress.com/2015/07/01/prince2-agile-in-onepicture/#:~:text=This%20framework%20is%20based%20on,the%20area%20of%20product%20delivery

asked 23/09/2024
Istvan Molnar
33 questions

Question 26

Report
Export
Collapse

Which role is responsible for facilitating the Agilometer assessment?

Project board
Project board
Project manager
Project manager
Team manager
Team manager
Customer subject matter expert
Customer subject matter expert
Suggested answer: B

Explanation:

Reference: https://www.axelos.com/news/blogs/september-2019/assessing-agile-factor-prince2-agiles-agileometer

asked 23/09/2024
Mitesh Solanki
47 questions

Question 27

Report
Export
Collapse

What is an epic?

A detailed user story with high business value
A detailed user story with high business value
The set of products handed over to the users
The set of products handed over to the users
A high-level user story that is quite broad or vague
A high-level user story that is quite broad or vague
A prioritized list of requirements to be delivered in a sprint
A prioritized list of requirements to be delivered in a sprint
Suggested answer: C

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?page=pra_160&showNav=true&expandNav=true

asked 23/09/2024
Vladimir Litvinenko
29 questions

Question 28

Report
Export
Collapse

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

To use empiricism, based on knowledge that comes from experience
To use empiricism, based on knowledge that comes from experience
To build, measure, learn from your experiences
To build, measure, learn from your experiences
To create a minimum viable product to manage uncertainty
To create a minimum viable product to manage uncertainty
To fail fast, if you are going to fail
To fail fast, if you are going to fail
Suggested answer: A

Explanation:

Reference:

https://publications.axelos.com/PRINCE2Agile2016/content.aspx?page=pra_127&showNav=true&expandNav=true

asked 23/09/2024
BurtAnderson Carter
35 questions

Question 29

Report
Export
Collapse

Which statement explains the setting of the cost tolerance for a project in an agile context?

Cost tolerance is flexed
Cost tolerance is flexed
Cost tolerance can be fixed or flexed
Cost tolerance can be fixed or flexed
Cost tolerance can be fixed and flexed
Cost tolerance can be fixed and flexed
Cost tolerance is fixed
Cost tolerance is fixed
Suggested answer: A

Explanation:

Reference: https://www.girlsguidetopm.com/inside-prince2-tolerances/#Cost_Tolerance

asked 23/09/2024
Tomasz Drobisz
29 questions

Question 30

Report
Export
Collapse

In Scrum, what answers the question ‘what can be done this sprint?’

Daily scrum
Daily scrum
Sprint review
Sprint review
Sprint planning
Sprint planning
Increment
Increment
Suggested answer: A
asked 23/09/2024
Marco Morsiani
45 questions
Total 92 questions
Go to page: of 10