Question 30 - PRINCE2 Agile Foundation discussion

Report
Export

In Scrum, what answers the question ‘what can be done this sprint?’

A.
Daily scrum
Answers
A.
Daily scrum
B.
Sprint review
Answers
B.
Sprint review
C.
Sprint planning
Answers
C.
Sprint planning
D.
Increment
Answers
D.
Increment
Suggested answer: A