Question 5 - PRINCE2 Agile Foundation discussion

Report
Export

Which statement about the ‘directing a project’ process is CORRECT?

A.
The project board should attend regular project progress meetings
Answers
A.
The project board should attend regular project progress meetings
B.
The project board should make decisions based on the Agilometer risks
Answers
B.
The project board should make decisions based on the Agilometer risks
C.
A project board member should fulfill the product owner role within a delivery team
Answers
C.
A project board member should fulfill the product owner role within a delivery team
D.
The project board should increase the stage-level time tolerance
Answers
D.
The project board should increase the stage-level time tolerance
Suggested answer: C

Explanation:

Reference: https://www.prince2primer.com/directing-a-project-3/