Question 90 - PRINCE2 Agile Foundation discussion

Report
Export

Which statement about the ‘be on time and hit deadlines’ target is CORRECT?

A.
It allows change to be handled dynamically
Answers
A.
It allows change to be handled dynamically
B.
It is achieved by keeping the delivery teams stable
Answers
B.
It is achieved by keeping the delivery teams stable
C.
It helps with planning dependencies within a project
Answers
C.
It helps with planning dependencies within a project
D.
It ensures that the level of quality is protected
Answers
D.
It ensures that the level of quality is protected
Suggested answer: C