Why is Lean Startup included in the ‘starting up a project’ process in PRINCE2 Agile?
A.
Because it explains how a small company can grow using traditional technologies
B.
Because it is designed to manage projects, delivering products in timeboxes
C.
Because it enables agile to be used in challenging and uncertain situations
D.
Because running a project and setting up a new business are the same