Question 16 - PRINCE2 Agile Foundation discussion
What needs to happen when new detailed requirements are added to a timebox?
A.
Requirements of a similar level of effort should be removed
B.
More people should be added to the delivery team
C.
The delivery milestones should be reviewed and re-planned
D.
Formal change control should be applied
Your answer: