Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

A.
It reduces testing in order to meet deadlines
Answers
A.
It reduces testing in order to meet deadlines
B.
It sets the project baseline at the correct level
Answers
B.
It sets the project baseline at the correct level
C.
It enables team dynamics to remain the same
Answers
C.
It enables team dynamics to remain the same
D.
It improves the supplier's reputation with the customer
Answers
D.
It improves the supplier's reputation with the customer
Suggested answer: A

Explanation:

Reference:

https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41