Question 43 - PRINCE2 Agile Foundation discussion

Report
Export

What should be decided when configuring PRINCE2 effectively?

A.
What to remove and where to add guidance
Answers
A.
What to remove and where to add guidance
B.
Where to put the emphasis and where to add guidance
Answers
B.
Where to put the emphasis and where to add guidance
C.
What to significantly change to create the right blend
Answers
C.
What to significantly change to create the right blend
D.
Which areas are not enabled to work with agile
Answers
D.
Which areas are not enabled to work with agile
Suggested answer: C