Related questions
Question 50 - PRINCE2 Agile Foundation discussion
How does agile address the risk associated with the project not being fully understood at the beginning?
A.
By allowing a lot of detail at the start
B.
By avoiding too much detail at the start
C.
By requiring details at the start
D.
By preventing the analysis of details at the start
Your answer: