What is typically displayed on a board to show progress to people working on a project?

A.
Agilometer assessment
Answers
A.
Agilometer assessment
B.
Product backlog
Answers
B.
Product backlog
C.
Information radiator
Answers
C.
Information radiator
D.
User story
Answers
D.
User story
Suggested answer: C