When tailoring the plans theme in an agile environment, what is recommended about using a Gantt chart?

It should be used when planning at the delivery level
It should be used when planning at the delivery level
It should be used when planning at the project level
It should be used when planning at the project level
It should be used when controlling the quality of the products delivered
It should be used when controlling the quality of the products delivered
It should be used when monitoring the amount of products delivered
It should be used when monitoring the amount of products delivered
Suggested answer: B
asked 23/09/2024
Bryan Smith
43 questions

Question 52

Report
Export
Collapse

Which statement about the ‘accept that the customer doesn't need everything’ target is CORRECT?

It is achieved by testing only a few features to deliver on time
It is achieved by testing only a few features to deliver on time
It is achieved by ensuring that the operational product has complete documentation
It is achieved by ensuring that the operational product has complete documentation
It is based on the concept that people generally use a limited number of product features
It is based on the concept that people generally use a limited number of product features
It enables a more accurate final product to be produced
It enables a more accurate final product to be produced
Suggested answer: C
asked 23/09/2024
Eduardo Cunha
30 questions

Question 53

Report
Export
Collapse

When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?

How to adapt the PRINCE2 management products
How to adapt the PRINCE2 management products
How to select which Agile framework should be favoured
How to select which Agile framework should be favoured
How to decide whether PRINCE2 is appropriate
How to decide whether PRINCE2 is appropriate
How to calculate the project budget and cost tolerance
How to calculate the project budget and cost tolerance
Suggested answer: A
asked 23/09/2024
Minh Phan
29 questions

Question 54

Report
Export
Collapse

What does velocity typically measure?

Work packages completed by the team
Work packages completed by the team
The rate of progress the team is making
The rate of progress the team is making
The number of timeboxes completed
The number of timeboxes completed
The speed that a minimum viable product is created
The speed that a minimum viable product is created
Suggested answer: B
asked 23/09/2024
Aaron Case
47 questions

Question 55

Report
Export
Collapse

Which TWO statements about the typical tailoring of a checkpoint report in an agile environment are CORRECT?

1) It should be replaced by the project manager attending a daily stand-up.

2) It should be displayed in the form of an information radiator in a team room.

3) It should be produced when the amount to be delivered will result in tolerance being exceeded.

4) It should be produced in a product backlog in the form of prioritized user stories.

1 and 2
1 and 2
2 and 3
2 and 3
3 and 4
3 and 4
1 and 4
1 and 4
Suggested answer: B
asked 23/09/2024
Farah Fauzi
41 questions

Question 56

Report
Export
Collapse

When creating the project product description, how should the purpose of the project product be defined?

As an opportunity
As an opportunity
As a vision
As a vision
As an outcome
As an outcome
As a goal
As a goal
Suggested answer: C
asked 23/09/2024
Victor Chacon
34 questions

Question 57

Report
Export
Collapse

Which is a purpose of the plans theme?

To identify any deviations from the project’s objectives
To identify any deviations from the project’s objectives
To control any approved changes to the baseline
To control any approved changes to the baseline
To monitor actual achievements against those planned
To monitor actual achievements against those planned
To communicate the approach for delivering products
To communicate the approach for delivering products
Suggested answer: D
asked 23/09/2024
Marcin Cieślak
43 questions

Question 58

Report
Export
Collapse

Which should be an objective of a retrospective?

To identify many process improvements and implement them
To identify many process improvements and implement them
To identify key process improvements to implement in the next sprint
To identify key process improvements to implement in the next sprint
To encourage the team to bond by allowing social activities to take place
To encourage the team to bond by allowing social activities to take place
To focus on objective learning rather than subjective feelings and emotions
To focus on objective learning rather than subjective feelings and emotions
Suggested answer: B
asked 23/09/2024
Nishan Perera
43 questions

Question 59

Report
Export
Collapse

What is typically displayed on a board to show progress to people working on a project?

Agilometer assessment
Agilometer assessment
Product backlog
Product backlog
Information radiator
Information radiator
User story
User story
Suggested answer: C
asked 23/09/2024
Antonio Carlos Figueiredo Junior
50 questions

Question 60

Report
Export
Collapse

How is the ‘learn from experience’ principle applied in an agile context?

By ensuring control through lots of short stages during innovative projects
By ensuring control through lots of short stages during innovative projects
By using the Agilometer to assess risks associated with the agile way of working
By using the Agilometer to assess risks associated with the agile way of working
By continual customer involvement to obtain feedback during the project
By continual customer involvement to obtain feedback during the project
By prioritizing quality criteria to focus the project on the delivery of value
By prioritizing quality criteria to focus the project on the delivery of value
Suggested answer: C