Which statement about the ‘directing a project’ process is CORRECT?

A.
The project board may pull reports from the information radiator
Answers
A.
The project board may pull reports from the information radiator
B.
As a minimum, the project board should receive oral reports from the project manager
Answers
B.
As a minimum, the project board should receive oral reports from the project manager
C.
The project board should attend the delivery team’s daily stand up meeting
Answers
C.
The project board should attend the delivery team’s daily stand up meeting
D.
The project board should receive regular reports focusing on cost and time overruns
Answers
D.
The project board should receive regular reports focusing on cost and time overruns
Suggested answer: A