If burndown charts are used to visualize progress, what do they track?

A.
Accumulated cost.
Answers
A.
Accumulated cost.
B.
Individual worker productivity.
Answers
B.
Individual worker productivity.
C.
Work remaining across time.
Answers
C.
Work remaining across time.
D.
Accumulated business value delivered to the customer.
Answers
D.
Accumulated business value delivered to the customer.
Suggested answer: C