How is management external to the Scrum Team involved in the Daily Scrum?

A.
The Scrum Master speaks on their behalf.
Answers
A.
The Scrum Master speaks on their behalf.
B.
The Development Team self-manages and is the only management required at the Daily Scrum.
Answers
B.
The Development Team self-manages and is the only management required at the Daily Scrum.
C.
Management gives an update at the start of each Daily Scrum.
Answers
C.
Management gives an update at the start of each Daily Scrum.
D.
The Product Owner represents their opinions.
Answers
D.
The Product Owner represents their opinions.
Suggested answer: B