Which best describes the Product Backlog?

A.
It is allowed to grow and change as more is learned about the product and its customers.
Answers
A.
It is allowed to grow and change as more is learned about the product and its customers.
B.
It provides just enough information to enable a Scrum team to start the design phase of a product.
Answers
B.
It provides just enough information to enable a Scrum team to start the design phase of a product.
C.
It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.
Answers
C.
It contains all foreseeable tasks and requirements from which the Scrum team can develop and maintain a complete project plan.
D.
It is baselined to follow change management processes.
Answers
D.
It is baselined to follow change management processes.
Suggested answer: A