Question 159 - PSM I discussion
One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (Choose two.)
A.
A shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal.
B.
An update of completed tasks and of the remaining work so the Scrum Master can plan the next day.
C.
A status report for the upper management indicating what each individual has done, will be doing, and what is impending him/her.
D.
An updated Scrum board to make Sprint progress transparent for the stakeholders.
E.
New impediments for the Scrum Master to take care of.