Scrum PSM I Practice Test - Questions Answers, Page 17
List of questions
Question 161
How do you know that a Development Team is cross-functional?
Question 162
Why does a Development Team need a Sprint Goal?
Question 163
Which three behaviors demonstrate that a team is self-organizing? (Choose three.)
Question 164
When does the next Sprint begin?
Question 165
Who should know the most about the progress toward a business objective or a release?
Question 166
What are two ways that architecture and infrastructure are handled in Scrum? (Choose two.)
Question 167
A Scrum Master is keeping a list of open impediments, but it is growing and they have been able to resolve only a small portion of the impediments. Which two techniques would be most helpful in this situation? (Choose two.)
Question 168
When many Development Teams are working on a single product, what best describes the definition of "Done"? (Choose the best answer.)
Question 169
The IT manager asks a Development Team for a status report describing the progress throughout the Sprint. The Development Team asks the Scrum Master for advice. The Scrum Master should:
(Choose the best answer.)
Question 170
When a Development Team determines that it will not be able to finish the complete forecast, who has to be present when reviewing and adjusting the Sprint work selected? (Choose the best answer.)
Question