List of questions
Related questions
Question 176 - PSM I discussion
How is management external to the Scrum Team involved in the Daily Scrum? (Choose the best answer.)
A.
The Scrum Master speaks on their behalf.
B.
Managers are not required at the Daily Scrum.
C.
Management gives an update at the start of each Daily Scrum.
D.
The Product Owner represents their opinions.
Your answer:
0 comments
Sorted by
Leave a comment first