Which two activities will a Product Owner engage in during a Sprint? (Choose two.)

A.
Run the Daily Scrum.
Answers
A.
Run the Daily Scrum.
B.
Prioritize the Development Team's work on the Sprint Backlog.
Answers
B.
Prioritize the Development Team's work on the Sprint Backlog.
C.
Update management on what is being worked on.
Answers
C.
Update management on what is being worked on.
D.
Answer questions from the Development Team about items in the current Sprint.
Answers
D.
Answer questions from the Development Team about items in the current Sprint.
Suggested answer: C, D