As the Sprint Planning progresses, the Developers realize that the workload may be greater than their capacity to complete the work. Which two are valid actions?

(choose the best two answers)

A.
Recruit additional Developers before the work can begim
Answers
A.
Recruit additional Developers before the work can begim
B.
The Developers ensure that the Scrum Team is aware, start the Sprint, and monitor progress.
Answers
B.
The Developers ensure that the Scrum Team is aware, start the Sprint, and monitor progress.
C.
The Developers work overtime during this Sprint
Answers
C.
The Developers work overtime during this Sprint
D.
Cancel the Sprint
Answers
D.
Cancel the Sprint
E.
Remove or change selected Product Backlog items.
Answers
E.
Remove or change selected Product Backlog items.
Suggested answer: B, E

Explanation:

According to the Scrum Guide, two valid actions that the Developers can take when they realize that the workload may be greater than their capacity to complete the work are ensuring that the Scrum Team is aware, starting the Sprint, and monitoring progress, and removing or changing selected Product Backlog items. These actions are consistent with Scrum values and principles, such as transparency, adaptation, and collaboration. The other options are not valid actions, as they are either wasteful (such as recruiting additional Developers or canceling the Sprint) or unsustainable (such as working overtime).