Question 228 - PSM I discussion
When does a Sprint conclude?
(choose the best answer)
A.
When the Product Owner decides enough has been delivered to meet the Sprint Goal.
B.
When the Sprint Retrospective is complete.
C.
When all the tasks are completed by the Developers.
D.
When all Product Backlog items meet their Definition of Done.