ExamGecko
Question list
Search
Search

List of questions

Search

Related questions











Question 41 - PSM II discussion

Report
Export

Your Scrum Team has been working together for over a dozen Sprints. The Scrum Team consists of 10 members. Each Sprint takes four weeks. As a Scrum Master, you observe that the Developers are hardly collaborating; during the Sprint, members are primarily working on their own items. You also notice that the items on the Sprint Backlog are mostly unrelated. You suspect that the lack of a Sprint Goal might be the cause.

Although you have encouraged the use of a Sprint Goal, both the Product Owner and the Developers have concluded that they are unable to create Sprint Goals based on the wide variety of items on their Product Backlog.

What might explain why this Scrum Team is struggling to craft a Sprint Goal?

(choose all that apply)

A.
Scrum might not be the best framework for the work done by this team.
Answers
A.
Scrum might not be the best framework for the work done by this team.
B.
The Sprints are too long.
Answers
B.
The Sprints are too long.
C.
The Product Owner does not have the mandate to make decisions about items on the Product Backlog nor their ordering.
Answers
C.
The Product Owner does not have the mandate to make decisions about items on the Product Backlog nor their ordering.
D.
The Product Owner is not communicating the Product Goal that they want to achieve in upcoming Sprints.
Answers
D.
The Product Owner is not communicating the Product Goal that they want to achieve in upcoming Sprints.
E.
The Scrum Team is too big.
Answers
E.
The Scrum Team is too big.
Suggested answer: B, D, E

Explanation:

The possible explanations for why this Scrum Team is struggling to craft a Sprint Goal are B, D, and E.

B) The Sprints are too long. A four-week Sprint is the maximum duration allowed by the Scrum Guide, and it may not be suitable for complex and uncertain work that requires frequent feedback and adaptation. A shorter Sprint may help the Scrum Team to focus on a clear and coherent Sprint Goal that aligns with the Product Goal and delivers a valuable Increment.

D) The Product Owner is not communicating the Product Goal that they want to achieve in upcoming Sprints. The Product Goal is a long-term objective for the Scrum Team that provides direction and purpose for their work. The Product Owner is responsible for communicating the Product Goal to the Developers and collaborating with them to create Sprint Goals that move them closer to the Product Goal. Without a clear Product Goal, the Scrum Team may lack a shared vision and end up working on unrelated items.

E) The Scrum Team is too big. The Scrum Guide recommends that the Scrum Team consists of 10 or fewer people, including the Scrum Master and the Product Owner. A larger team may have difficulties in collaborating effectively, self-organizing, and creating a meaningful Sprint Goal that reflects the collective commitment of the Developers. A smaller team may improve the communication, coordination, and cohesion among the Developers and help them to create and achieve a Sprint Goal.

The Scrum Guide, section 2.3 (The Scrum Team), page 7

The Scrum Guide, section 3.1 (The Sprint), page 8

The Scrum Guide, section 3.3 (The Sprint Goal), page 9

The Scrum Guide, section 4.1 (The Product Backlog), page 11

The Scrum Master Learning Path, module 2 (The Scrum Framework), lesson 2 (The Sprint) and lesson 3 (The Sprint Goal)

asked 23/09/2024
First Last
36 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first