You have just been hired as a Scrum Master by a company new to Scrum. The company wants to use Scrum to build a new product that was conceived by the product management department. You will be the Scrum Master of two new teams that will build a first version of the product. The product management department assigns two new Product Owners, but wants more advice about the required participation with the new Scrum Teams. Which two suggestions would you offer?

(choose the best two answers)

A.
Having one Product Owner will improve the clarity of accountability to the teams and to the product management department.
Answers
A.
Having one Product Owner will improve the clarity of accountability to the teams and to the product management department.
B.
Two Product Owners are necessary, one for each Scrum Team. They report to an overarching chief Product Owner.
Answers
B.
Two Product Owners are necessary, one for each Scrum Team. They report to an overarching chief Product Owner.
C.
Each Scrum Team has a separate Product Backlog, holding each team's assigned requirements.
Answers
C.
Each Scrum Team has a separate Product Backlog, holding each team's assigned requirements.
D.
A single Product Backlog should be maintained holding all requirements for the new product.
Answers
D.
A single Product Backlog should be maintained holding all requirements for the new product.
Suggested answer: A, D

Explanation:

A) Having one Product Owner will improve the clarity of accountability to the teams and to the product management department. This is a good suggestion, as it ensures that there is a single person who is responsible for maximizing the value of the product and managing the Product Backlog. Having one Product Owner also avoids confusion, duplication, or conflict among multiple Product Owners who may have different visions, priorities, or expectations for the product.

D) A single Product Backlog should be maintained holding all requirements for the new product. This is also a good suggestion, as it ensures that there is a single source of truth for the product requirements and that they are transparent and visible to all stakeholders. Having a single Product Backlog also enables the Product Owner to order the items based on their value, risk, dependency, and urgency, and to collaborate with the Scrum Teams to select and refine the items for each Sprint.

The Scrum Guide, section 2.3 (The Scrum Team), page 7

The Scrum Guide, section 4.1 (The Product Backlog), page 11

The Scrum Master Learning Path, module 2 (The Scrum Framework), lesson 4 (Sprint Planning) and lesson 5 (The Sprint Review)