Which two of these situations best demonstrate that a Scrum Team is self-managing?
(choose the best two answers)
A.
Developers collaboratively select and re-plan their work during the Sprint.
B.
The Scrum Team invites the right external people to the Sprint Planning to help them create a complete and detailed Sprint Backlog before the meeting timebox expires.
C.
The Developers create their own Sprint Backlog, reflecting all work that is part of the Definition of Done.
D.
Management is invited to the Daily Scrum for a progress update and subsequently works with the Scrum Master to optimize the plan for the next day.
E.
The Developers are strictly working within the boundaries of their function description, and are handing off work in a timely fashion to the other members within the team.
Your answer: