What is the primary concern when multiple Scrum Teams work from the same Product Backlog with the goal of creating a valuable and useful integrated Increment by the end of their Sprint?
(choose the best answer)
A.
Minimizing dependencies between Scrum Teams.
B.
Clearly defining all requirements three Sprints ahead.
C.
Maximizing velocity.
D.
Making sure there is enough work for everyone on every team.