Question 67 - PSM II discussion
During a Sprint Review, the Product Owner determines that she is going to release the current Increment to production. The stakeholders ask to stop the Sprint to react more quickly to the user feedback that is expected after this release. The Product Owner prefers to continue the Sprint to make progress with the next release. You facilitate a discussion on how to proceed.
What are two acceptable results of this discussion?
(choose the best two answers)
A.
Continue sprinting but shorten the Sprint length to allow for shorter feedback loops.
B.
Stop sprinting and let the Developers work on new customer requests as they arise.
C.
Continue sprinting and include the customer feedback in the Product Backlog.
D.
Continue sprinting but allow customer feedback to change the Sprint Goal within the Sprint.
Your answer:
0 comments