A company has a Dynamics 365 Supply Chain Management implementation. The company plans a promotional sales campaign that targets top customers.
The sales campaign will guarantee that orders are delivered within a specific two-week period.
The system configuration must prioritize a group of similar production orders so they can be scheduled at the same time.
You need to configure the system.
What should you create?
Production pool
Production group
Production flow model
Production unit
A company plans to use master planning in Dynamics 365 Supply Cha-n Management. The company will sell items between legal entities.
The company has several facilities across legal entities that can manufacture the same productsSome products are produced only in some plants. To meet product demand, when one facility rs over capacity, another facility is used to fulfill the downstream demand.
The organizational entities are:
• Legal Entity A: Plant 1,2, and 3
• Legal Entity B: Plant 4 and S
• Legal Entity C: Plant 6. 7. and 8
The following plants must be planned together
• Plan1, Plant 3, and Plant 4
• Plant 2, Plant 6, and Plant 8
• Plant 5 and Plant 7
You need to configure master planning for the facilities. Which configuration mechanism should you use?
Intercompany planning groups
Coverage groups
Item model groups
Production groups
HOTSPOT
A manufacturing company uses Dynamics 365 Supply Cham Management.
The company identifies a bill of materials (BOM) item that needs to be recalled for a product The engineering department needs to link customer support incidents and knowledgebase articles related to the product change.
Other items affected by this change must reference the same support incidents and knowledgebase articles.
You need to recommend features to facilitate this business process.
Which features should you recommend? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
A manufacturing company is implementing production in Dynamics 365 Supply Chain Management.
The production scheduler requires that machines not be scheduled to run concurrently when planning production. The scheduler also must be able to see the scheduling m a graphical view.
You need to configure the system to meet the requirements.
Which three options should you configure? Each answer presents a partial solution.
NOTE: Each correct selection is worth one point
finite capacity
Capable to Promise
bottleneck resource
job scheduling
operations scheduling
A company that makes artisan chocolate is implementing Dynamics 365 Supply Chain Management.
To safeguard the quality of its ingredients, the company limits recipe substitutions of its chocolates.
its top-selling chocolate bar must contain 20 percent sugar. The sugar can be Obtained from either cane or beet sugar depending on supply at the time of production.
The system must be able to automatically substitute the appropriate sugar items when generating production orders to meet the quality level of sugar even when the preferred concentration of cane sugar is out of stock.
You need to configure the system.
Which three components must you configure? Each correct answer presents part of the solution.
NOTE: Each correct selection is worth one point.
Item model group
Priority
BOM lines
Item allocation key
Plan group
Formula lines
DRAG DROP
You are a manufacturer using Dynamics 365 Supply Chain Management.
A new series of orders is authorized for production.
You need to identify which documents to use for the released production order.
Which document should you use for each requirement? To answer, drag the appropriate documents to the correct requirements. Each document may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
DRAG DROP
A company uses Dynamics 365 Supply Cham Management.
Several production orders are in the started status.
An issue with equipment causes a rollback in the production status tor some of the orders.
Some orders must be reset once the equipment is repaired, based on which products were being manufactured.
You need to reset the production orders based on the requirements Which status should you use for each requirement? To answer, drag the appropriate statuses to the correct requirements. Each status may be used once, more than once, or not at all.
You may need to drag the split bar between panes or scroll to view content.
DRAG DROP
A manufacturing company is implementing Dynamics 365 Supply Cham Management.
Bill of materials (BOMs) must be calculated using standard cost principles.
Miscellaneous charges must be included in the unit cost price. The explosion mode must arways be enforced as single level.
You need to configure the system to meet the requirements.
Which configuration should you enable for each requirement? To answer, drag the appropriate configurations to the correct requirements. Each configuration may be used once, more than once, or not at all. You may need to drag the split bar between panes or scroll to view content.
NOTE: Each correct selection is worth one point.
HOTSPOT
A specialty nutritional supplement manufacturer that produces vitamins uses Dynamics 365 Supply Cham Management. The vitamins are configured as a single product but have multiple sellable variations by volume.
Multiple vendors send bulk raw ingredients to the manufacturer on a quarterly basis.
The vendors own the raw ingredients until the manufacturer receives an order from a distributer for a product. The manufacturer then must own the raw ingredients to be able to process the vendor invoice and provide payments for the required amounts of the raw ingredients.
Any remaining raw ingredients that are unsold and at the end of their shelf life must be removed from storage and shipped back to the vendors.
A company implements Dynamics 365 Supply Chain Management and configures the system to support process manufacturing.
The company manufactures pain-relieving lotions. Several of the primary ingredients are delivered at different concentrations depending on the ingredient and vendor. Ingredient A is the primary active ingredient In the lotion. Ingredients is used as a compensating ingredient.
You need to ensure that the system is set up to support the manufacturing process.
Solution: Set up the batch attributes for a minimum value, a maximum value, and a target level for the filler ingredients.
Does the solution meet the goal?
Yes