ExamGecko
Home / Microsoft / MB-320 / List of questions
Ask Question

Microsoft MB-320 Practice Test - Questions Answers, Page 4

List of questions

Question 31

Report
Export
Collapse

HOTSPOT

A company produces light projection toys for holiday decorations. The company plans to implement Lean manufacturing processes.

Production master data must meet the following requirements:

Visual templates for a holiday must only be included for in-store products where that holiday is celebrated

Visual templates for a holiday must only be included for in-store products based upon that season

Online customers must be able to order visual templates for any holiday or region.

You need to implement production master data.

What should you configure? To answer, select the appropriate options in the answer area.

NOTE: Each correct selection is worth one point.


Microsoft MB-320 image Question 31 101911 10052024010019000
Correct answer: Microsoft MB-320 image answer Question 31 101911 10052024010019000
asked 05/10/2024
adnan reubin
30 questions

Question 32

Report
Export
Collapse

DRAG DROP

A company uses manufacturing execution for processing of production orders. Multiple production orders from last week need to be ended.

You need to process the time registrations to allow the orders to end.

Which four steps should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


Microsoft MB-320 image Question 32 101912 10052024010019000
Correct answer: Microsoft MB-320 image answer Question 32 101912 10052024010019000
asked 05/10/2024
chanon witchajutakul
28 questions

Question 33

Report
Export
Collapse

DRAG DROP

A company uses warehouse management and manufacturing execution to process their production orders.

You configure the manufacturing execution production order defaults to always consume Bill of materials (BOM) components when an operation step is completed in the job registration terminal. You create a production order. The order is in released status.

You need to process this order all the way through to end status.

Which four actions should you perform in sequence? To answer, check the appropriate actions to the answer area and arrange them in the correct order.


Microsoft MB-320 image Question 33 101913 10052024010019000
Correct answer: Microsoft MB-320 image answer Question 33 101913 10052024010019000
asked 05/10/2024
Szymon Strzep
39 questions

Question 34

Report
Export
Collapse

HOTSPOT

You are the production scheduler for a manufacturing company. You have run the Resource Group Capacity report as shown in the Resource Group 21 Capacity exhibit. (Click the Resource Group 21 Capacity tab).

Microsoft MB-320 image Question 34 101914 10052024010019000000

After reviewing that report, you run Resource Capacity reports as shown in the Resource 2101 and 2102 Capacity exhibits. (Click the 2101 Capacity and 2102 Capacity tabs.)

Microsoft MB-320 image Question 34 101914 10052024010019000000

Microsoft MB-320 image Question 34 101914 10052024010019000000

You run the Gantt chart report as shown in the Gantt exhibit to determine the production orders scheduled on the resources. (Click the Gantt tab.)

Microsoft MB-320 image Question 34 101914 10052024010019000000

You need to determine the method to schedule the production lines.

For each of the following statements, select Yes if the statement is true. Otherwise, select No.

NOTE: Each correct selection is worth one point.


Microsoft MB-320 image Question 34 101914 10052024010019000
Correct answer: Microsoft MB-320 image answer Question 34 101914 10052024010019000
asked 05/10/2024
Andre Beary
29 questions

Question 35

Report
Export
Collapse

HOTSPOT

You are the production scheduler at a manufacturing company. You schedule estimated production orders and ensure that capacity is used efficiently.

You have an order that must be scheduled at the resource group level and scheduled backward from the delivery date specified on the production order.

You need to schedule the order.

Which scheduling parameters should you use? To answer, select the appropriate option in the answer area.

NOTE: Each correct selection is worth one point.


Microsoft MB-320 image Question 35 101915 10052024010019000
Correct answer: Microsoft MB-320 image answer Question 35 101915 10052024010019000

Explanation:


References:

https://docs.microsoft.com/en-us/dynamics365/unified-operations/supply-chain/production-control/operation-scheduling-options

asked 05/10/2024
Kristian Michael Matias
44 questions

Question 36

Report
Export
Collapse

DRAG DROP

You manage pricing for a food processing company. The raw meat used by the business is a commodity-traded product and has a changing purchase price.

You must implement the commodity pricing module. You create a pricing template with margin data.

You need to calculate the cost price for the manufactured goods as well as the sales price based on margin standards.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.


Microsoft MB-320 image Question 36 101916 10052024010019000
Correct answer: Microsoft MB-320 image answer Question 36 101916 10052024010019000

Explanation:

asked 05/10/2024
Sharanjit Kareer
41 questions

Question 37

Report
Export
Collapse

You produce 100 total units of finished goods. The amount of material used to produce the goods is the equivalent amount of material needed to produce 105 finished goods.

The company must track variances in material compared to the original estimated amount. You must only use one picking list journal for each production order.

You need to post a picking list that accounts for the material required to produce 105 finished goods.

What should you do?

Post a picking list for 100 to account for the originally estimated amount. Post an additional picking list to account for the equivalent amount of material to produce 5 finished goods.

Post a picking list for 100 to account for the originally estimated amount. Post an additional picking list to account for the equivalent amount of material to produce 5 finished goods.

Report as finished five additional units into the good quantity and post a picking list for only the originally estimated amount.

Report as finished five additional units into the good quantity and post a picking list for only the originally estimated amount.

In the Bill of materials production details, edit the estimated amount for each line to equal 105 units of raw material.

In the Bill of materials production details, edit the estimated amount for each line to equal 105 units of raw material.

When creating the lines for a picking list, select the estimated consumption option and override the consumption field with the actual amount to be consumed.

When creating the lines for a picking list, select the estimated consumption option and override the consumption field with the actual amount to be consumed.

Suggested answer: D
asked 05/10/2024
Vahit Erciyas
44 questions

Question 38

Report
Export
Collapse

A customer produces light projection toys for holiday decorations throughout the year.

You are in the first month of a season. Production flows take one day to complete.

The floor supervisor reports that seasonal production targets will not be met. You review the Kanban schedule board and identify thousands of unplanned jobs.

You need to plan the jobs to be completed two weeks prior to the start of the next season.

What are two possible ways to achieve this goal? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

Set the Automatic planning option for each unscheduled job to Yes

Set the Automatic planning option for each unscheduled job to Yes

Manually schedule each unscheduled job on its due date

Manually schedule each unscheduled job on its due date

Set the Automatic planning option for each unscheduled job to No

Set the Automatic planning option for each unscheduled job to No

Manually schedule each unscheduled job forward from the date of the end of the season

Manually schedule each unscheduled job forward from the date of the end of the season

Manually schedule each unscheduled job to the next period of the start of the next season

Manually schedule each unscheduled job to the next period of the start of the next season

Manually schedule each unscheduled job to the previous period of the end of the next season

Manually schedule each unscheduled job to the previous period of the end of the next season

Suggested answer: A, F

Explanation:

Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/production-control/lean-manufacturing-kanban-job-scheduling

asked 05/10/2024
Henrik Persson
34 questions

Question 39

Report
Export
Collapse

A customer produces light projection toys for holiday decorations throughout the year. Vendors have negotiated rebate agreements as a condition of their contract. The contract also contains the visual templates required for the customer to use in a season.

Vendor rebate agreements must only be applied if the following requirements are met:

Units of measure for deliverables are the same unit of measure as on the agreement. The agreement is valid as of the date a purchase order is generated.

You need to configure the vendor rebate agreements.

What should you do?

Set the Calculation date type field value to Created

Set the Calculation date type field value to Created

Set the Cumulative purchase by field value to the end of the season date

Set the Cumulative purchase by field value to the end of the season date

Set the Rebate line break type field value to Quantity

Set the Rebate line break type field value to Quantity

Set the Cumulative purchase by field value to the beginning of the season date

Set the Cumulative purchase by field value to the beginning of the season date

Suggested answer: A

Explanation:

References: https://docs.microsoft.com/en-us/dynamics365/supply-chain/procurement/vendor-rebates

asked 05/10/2024
Hari Krishnan
34 questions

Question 40

Report
Export
Collapse

A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.

You need to optimize the planned production orders.

What should you do?

Rerun master planning. Select the static plan with a coverage time fence of two weeks.

Rerun master planning. Select the static plan with a coverage time fence of two weeks.

Firm the orders

Firm the orders

In Planned orders, combine the production orders

In Planned orders, combine the production orders

Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks

Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks

Suggested answer: A
asked 05/10/2024
Selim OZIS
32 questions
Total 203 questions
Go to page: of 21
Search

Related questions