A consultant is working to setup the network before starting the Foundation process.

How should the consultant complete this task?

A.
Using the shared IPMI port, ensure that the connected switch can auto-negotiate to 1 Gbps.
A.
Using the shared IPMI port, ensure that the connected switch can auto-negotiate to 1 Gbps.
Answers
B.
Disable IPv6 on the network to which the nodes are connected to ensure that IPv6 unicast is blocked.
B.
Disable IPv6 on the network to which the nodes are connected to ensure that IPv6 unicast is blocked.
Answers
C.
Ensure the IPMI of the nodes are reachable using pre-configured IPMI IPv6 addresses.
C.
Ensure the IPMI of the nodes are reachable using pre-configured IPMI IPv6 addresses.
Answers
D.
On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch.
D.
On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch.
Answers
Suggested answer: D

Explanation:

Before starting the Foundation process, the consultant should prepare the network by:

On Nutanix NX Series, connect the IPMI port and any one of the data ports to the switch: This ensures that the IPMI (for management and remote access) and at least one data port (for cluster communication and data traffic) are connected and operational, facilitating a smooth foundation process.

Nutanix Bible (https://www.nutanixbible.com), especially sections on initial hardware setup and network preparations.

Nutanix Hardware Setup Guide from Nutanix University (https://university.nutanix.com), detailing the specific steps for networking configurations during initial setup.

Before deploying a new 3-node cluster, a consultant wants to know which VLAN ID to use during Foundation.

Where can the consultant find this information?

A.
Nutanix Portal
A.
Nutanix Portal
Answers
B.
As-Built Guide
B.
As-Built Guide
Answers
C.
Deployment Questionnaire
C.
Deployment Questionnaire
Answers
D.
Test Plan
D.
Test Plan
Answers
Suggested answer: C

Explanation:

To find the correct VLAN ID to use during the Foundation of a new 3-node cluster, the consultant should refer to the:

Deployment Questionnaire: This document typically contains detailed pre-engagement information gathered from the customer, including network specifications such as VLAN IDs. It provides the necessary context and configurations needed for a successful deployment.

Nutanix Bible (https://www.nutanixbible.com), where the importance of pre-deployment planning and documentation is highlighted.

Nutanix University: NCS-Core 6.8 Training (https://university.nutanix.com), which covers the process of gathering and using deployment information.

After an onsite cluster deployment, a consultant prepares the deliverables for a project closeout.

Which two data in the As-Built Guide require adjustment or might be missing completely? (Choose two.)

A.
Nutanix Node Port Layout
A.
Nutanix Node Port Layout
Answers
B.
AHV Host information
B.
AHV Host information
Answers
C.
Physical Rack Layout
C.
Physical Rack Layout
Answers
D.
Cluster information
D.
Cluster information
Answers
Suggested answer: A, C

Explanation:

After an onsite cluster deployment, the As-Built Guide is a crucial document that provides detailed information about the final configuration of the system. However, certain data in the As-Built Guide might require adjustment or might be missing completely.

In this case, the Nutanix Node Port Layout (Option A) and the Physical Rack Layout (Option C) are two data that might require adjustment or might be missing completely. The Nutanix Node Port Layout provides a visual representation of the network connections for each node in the cluster, while the Physical Rack Layout provides a visual representation of the physical arrangement of the nodes in the rack. Both of these data are crucial for understanding the physical and network configuration of the cluster, and any inaccuracies or omissions in these data could lead to confusion or issues in the future.

Therefore, the consultant should ensure that the Nutanix Node Port Layout and the Physical Rack Layout in the As-Built Guide are accurate and complete.

[Nutanix Support & Insights]

[Nutanix Community]

[Nutanix Documentation]

[Nutanix Certified services - core (NCS-Core) 6.8 - Nutanix University]

[Nutanix Bible]

[Nutanix Certified services - core (NCS-Core) 6.8 Playlist - YouTube]

A consultant is reviewing a customers Pre-delivery Questionnaire.

The customer wants to deploy their cluster with ESXi as the hypervisor with vSphere Distributed Switch. The customer will be using Cisco Nexus 9k as their switch choice In the kick-off call, it is confirmed that the customer has a business requirement to use LACP in their environment.

What should the consultant ensure that the customer configures on the port-channel interface before deployment?

A.
show pore-channel
A.
show pore-channel
Answers
B.
no lacp graceful-convergence
B.
no lacp graceful-convergence
Answers
C.
service unsupported-transceiver
C.
service unsupported-transceiver
Answers
D.
no lacp suspend-individual
D.
no lacp suspend-individual
Answers
Suggested answer: D

Explanation:

Given that the customer is using a Cisco Nexus 9k switch and wants to deploy ESXi with a vSphere Distributed Switch while using LACP, the consultant should ensure that the customer configures:

D . no lacp suspend-individual: This command ensures that LACP doesn't suspend the individual port if it does not receive LACP PDUs from the other side, which is crucial in environments where continuous connectivity is required for all member links of the port-channel to maintain uninterrupted network services.

Nutanix Bible (https://www.nutanixbible.com), where it discusses ESXi configurations and switch settings.

Cisco Nexus configuration guides, referred through Nutanix's training materials, which recommend settings for optimal integration with Nutanix environments.

A consultant is preparing for a cluster deployment and evaluates portable Foundation.

Laptop configuration is as follows:

* CPU: 2.8 GHz Quad-Core Intel Core i7

* Memory: 4GB RAM

During the installation, the consultant encounters some errors and tries to troubleshoot.

What could prevent successful installation and Foundation usage?

A.
Gatekeeper must be enabled
A.
Gatekeeper must be enabled
Answers
B.
Oracle VirtualBox is installed on the laptop
B.
Oracle VirtualBox is installed on the laptop
Answers
C.
Laptop configuration does not meet installation requirements
C.
Laptop configuration does not meet installation requirements
Answers
D.
Firewall Stealth Mode is disabled
D.
Firewall Stealth Mode is disabled
Answers
Suggested answer: C

Explanation:

The likely reason for encountering errors during the installation and use of the portable Foundation tool on the laptop described is:

C . Laptop configuration does not meet installation requirements: The Foundation tool, being a resource-intensive application, typically requires more than 4GB RAM to function efficiently, especially when deploying larger or more complex environments.

Nutanix Bible (https://www.nutanixbible.com), especially sections on Foundation requirements.

Nutanix University: NCS-Core 6.8 Training (https://university.nutanix.com), which includes specifications for hardware requirements for deployment tools.

After deployment of a Nutanix cluster, a customer has requested to validate the peak performance of the cluster.

Which tool can a consultant use to satisfy this request?

A.
Nutanix X-Ray
A.
Nutanix X-Ray
Answers
B.
Nutanix HCiBench
B.
Nutanix HCiBench
Answers
C.
diagnostics.py
C.
diagnostics.py
Answers
D.
Nutanix perfmon
D.
Nutanix perfmon
Answers
Suggested answer: A

Explanation:

To validate the peak performance of a deployed Nutanix cluster, the consultant can use:

A . Nutanix X-Ray: X-Ray is a performance testing tool specifically designed for Nutanix environments, capable of simulating a variety of workloads and scenarios to measure and report on the cluster's performance capabilities.

Nutanix Bible (https://www.nutanixbible.com), where X-Ray and its capabilities are detailed.

Nutanix University: NCS-Core 6.8 Training (https://university.nutanix.com), which covers performance testing and validation using X-Ray.

A consultant attempts to perform an LCM inventory after successfully creating the cluster, but is met with the following error:

LCM Exception [LcmExceptionHandler]: Could not find a module for entity with reference name nutanix.ncc.update

What is the most likely reason LCM inventory/update is failing?

A.
Nameservers are not reachable.
A.
Nameservers are not reachable.
Answers
B.
IPMI network is unable to reach the internet.
B.
IPMI network is unable to reach the internet.
Answers
C.
Clusters must be licensed before LCM inventory.
C.
Clusters must be licensed before LCM inventory.
Answers
D.
Nutanix CVMs are blocking TCP port 54.
D.
Nutanix CVMs are blocking TCP port 54.
Answers
Suggested answer: C

Explanation:

The error encountered during the LCM inventory process, which mentions 'Could not find a module for entity with reference name nutanix.ncc.update,' typically indicates that the cluster has not yet been licensed. The Life Cycle Management (LCM) functionality in Nutanix systems requires a valid license to perform operations such as inventory checks and updates. Without this license, LCM cannot retrieve or update the necessary software modules, leading to the stated error. Licensing the cluster would resolve this issue and allow the LCM processes to proceed normally.

Reference: Nutanix LCM Documentation, Nutanix Licensing Guidelines.

During the knowledge transfer session, a consultant conducts a storage management demo. In the Creating a Storage Container workflow, the customer notices the Advertised Capacity parameter and asks for an explanation.

How should the consultant respond?

A.
It is a capacity computed by dividing physical storage usage of a container by the replication factor (RF).
A.
It is a capacity computed by dividing physical storage usage of a container by the replication factor (RF).
Answers
B.
It assists in reserving space for a storage container to ensure a maximum storage capacity is available.
B.
It assists in reserving space for a storage container to ensure a maximum storage capacity is available.
Answers
C.
It enables the ability to cap usage of storage containers to be smaller than the limit of a storage pool capacity.
C.
It enables the ability to cap usage of storage containers to be smaller than the limit of a storage pool capacity.
Answers
D.
It assists in reserving space for a storage container to ensure a minimum storage capacity is available.
D.
It assists in reserving space for a storage container to ensure a minimum storage capacity is available.
Answers
Suggested answer: C

Explanation:

The 'Advertised Capacity' parameter in the context of creating a storage container in Nutanix systems is used to cap the usage of storage containers to be smaller than the limit of a storage pool's capacity. This feature allows administrators to set a maximum storage limit for a container, preventing it from using the entire storage pool's capacity and ensuring that resources are allocated based on planned capacity requirements. This helps in maintaining predictable storage management and allocation within a Nutanix environment.

Reference: Nutanix Storage Container Management Documentation, Nutanix Best Practices for Storage Configuration.

A customer's security team has a policy prohibiting a consultant's laptop from connecting within the corporate datacenter.

In which two ways should the consultant complete the customer deployment on the factory-prepared nodes? (Choose two.)

A.
Use the Controller VM-based Foundation process.
A.
Use the Controller VM-based Foundation process.
Answers
B.
Configure IPs on hosts and create the cluster.
B.
Configure IPs on hosts and create the cluster.
Answers
C.
Run the Network Crashcart Script, provide IPs, and create the cluster manually.
C.
Run the Network Crashcart Script, provide IPs, and create the cluster manually.
Answers
D.
Manually edit ifcfg-etho file on CVM, restart networking, and create the cluster.
D.
Manually edit ifcfg-etho file on CVM, restart networking, and create the cluster.
Answers
Suggested answer: A, C

Explanation:

Given that the customer's security policy prohibits connecting a consultant's laptop within the corporate datacenter, the consultant can complete the deployment using:

A . The Controller VM-based Foundation process, which allows the consultant to configure and deploy the cluster using the software tools provided within the Controller VM itself. This method does not require direct laptop connection to the network. C. Run the Network Crashcart Script to manually configure IP addresses on the hosts and then proceed to create the cluster manually. This approach involves using available scripts and utilities that can be executed from within the data center's management interfaces without needing direct laptop access. Options B and D would typically require direct network connection capabilities not permissible under the security constraints.

Reference: Nutanix Foundation Documentation, Nutanix Deployment Best Practices.

Refer to Exhibit:

A customer is preparing to expand a cluster with a consultant. The production cluster is comprised of one NX-3460-G7 and two NX-8235 G8 blocks. The running AOS version is 5.20.4.6 and Hypervisor version is ESXi 6.7 U3b. vCenter is also running a 6.7 version.

One NX-3235-G9 block will be added to that cluster (ESXI-NUTA-09 and ESXI-NUTA-10).

The consultant has verified Nutanix documentation and customer's As-Built guide:

* NX-3060-G7 and NX-8035-G8 are hybrid HCI nodes

* ESXi 6.7 U3b is unsupported for the new G9 hardware model

* AOS 5.20.X and ESXi 6 X are end of support

* NX-3060-G7 and NX-8035-G8 hypervisors can be upgraded to the latest ESXi supported version

What actions should be taken before beginning the cluster expansion?

A.
Upgrade vCenter, AOS and ESXi to supported and recommended versions.
A.
Upgrade vCenter, AOS and ESXi to supported and recommended versions.
Answers
B.
Upgrade only AOS and ESXi to supported and recommended versions.
B.
Upgrade only AOS and ESXi to supported and recommended versions.
Answers
C.
Replace all HDDs with SSDs on the Production cluster.
C.
Replace all HDDs with SSDs on the Production cluster.
Answers
D.
Prepare Foundation and the whitelist. json file to deploy ESXi 6.7 U3b on the new nodes.
D.
Prepare Foundation and the whitelist. json file to deploy ESXi 6.7 U3b on the new nodes.
Answers
Suggested answer: A

Explanation:

Before expanding the cluster with the new NX-3235-G9 block, it is critical to ensure that all components are running supported and recommended versions due to compatibility and support issues. Therefore, the necessary actions include: A. Upgrade vCenter, AOS, and ESXi to supported and recommended versions. This step ensures compatibility across all components, particularly important as the new G9 hardware does not support the currently installed version of ESXi. Upgrading these components will also ensure continued vendor support and the stability of the environment. Options B, C, and D do not adequately address the need for vCenter upgrades or the fact that ESXi 6.7 U3b is unsupported for G9, highlighting the necessity for a comprehensive upgrade.

Reference: Nutanix Hardware Compatibility List, Nutanix Support Portal.