A company has a Dynamics 365 Supply Chain Management implementation. The company plans a promotional sales campaign that targets top customers.

The sales campaign will guarantee that orders are delivered within a specific two-week period.

The system configuration must prioritize a group of similar production orders so they can be scheduled at the same time.

You need to configure the system.

What should you create?

A.

Production pool

Answers
A.

Production pool

B.

Production group

Answers
B.

Production group

C.

Production flow model

Answers
C.

Production flow model

D.

Production unit

Answers
D.

Production unit

Suggested answer: A