Question 19 - C_TS422_2023 discussion
What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?
A.
MRP creates a dependent requirement.
B.
A sales order is delivered.
C.
MRP creates a planned order.
D.
A sales order is created.