What is a prerequisite for consumption of planned independent requirements to take place for planning strategy 40 (Planning with final assembly)?

A.

MRP creates a dependent requirement.

Answers
A.

MRP creates a dependent requirement.

B.

A sales order is delivered.

Answers
B.

A sales order is delivered.

C.

MRP creates a planned order.

Answers
C.

MRP creates a planned order.

D.

A sales order is created.

Answers
D.

A sales order is created.

Suggested answer: D