What are some benefits of planning with planned independent requirements for finished materials? Note: There are 2 correct answers to this question.

A.

Reduced delivery times

Answers
A.

Reduced delivery times

B.

Reduced times for final assembly

Answers
B.

Reduced times for final assembly

C.

Option to forecast planning for production resources

Answers
C.

Option to forecast planning for production resources

D.

Option to use maketoorder production

Answers
D.

Option to use maketoorder production

Suggested answer: A, B