Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.

A.

In which storage location is the BOM required?

Answers
A.

In which storage location is the BOM required?

B.

Is the material type allowed in the BOM?

Answers
B.

Is the material type allowed in the BOM?

C.

Which base unit of measure does the material have?

Answers
C.

Which base unit of measure does the material have?

D.

What status does the BOM have?

Answers
D.

What status does the BOM have?

Suggested answer: B, D