What are the possible results of a production planning run in Advanced Planning (PP/DS)? Note: There are 2 correct answers to this question.

A.

Planned order

Answers
A.

Planned order

B.

Scheduling agreement schedule line

Answers
B.

Scheduling agreement schedule line

C.

Production order

Answers
C.

Production order

D.

Purchase order

Answers
D.

Purchase order

Suggested answer: A, B