Question 15 - PMI-RMP discussion

Report
Export

A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.

Which risk identification technique should the risk manager use?

A.

Prompt lists

Answers
A.

Prompt lists

B.

Interviews

Answers
B.

Interviews

C.

Delphi technique

Answers
C.

Delphi technique

D.

Nominal group technique

Answers
D.

Nominal group technique

Suggested answer: D

Explanation:

The risk identification technique that the risk manager should use is the nominal group technique. This technique involves bringing stakeholders together to brainstorm potential risks and then ranking them based on their importance. This allows for interaction and collaboration among stakeholders, which can help ensure that an exhaustive list of risks is created.

The nominal group technique is a risk identification technique that involves the interaction and collaboration of stakeholders to generate an exhaustive list of risks. It is a structured process that allows each participant to share their ideas independently, then rank and prioritize them as a group.This technique ensures that all opinions are considered and reduces the influence of dominant or biased individuals12

.