A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.
Which risk identification technique should the risk manager use?
A.
Prompt lists
B.
Interviews
C.
Delphi technique
D.
Nominal group technique
Your answer: