Question 17 - PMI-RMP discussion
The project manager wants to use an objective method to evaluate the key project risks and develop response plans.
What action should the risk manager propose?
A.
Ask the team to perform an earned value analysis.
B.
Review the lessons learned from other projects.
C.
Ask the team to prepare a Monte Carlo analysis.
D.
Ask the risk expert to perform a PESTLE evaluation.