List of questions
Related questions
Question 38 - PMI-RMP discussion
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
Provided regular training to the risk owners for plan implementation
Determined risk triggers and thresholds in the risk response plan
Increased communications to influence stakeholder risk responses
Updated the project schedule, adding risk owner implementation tasks.
0 comments
Leave a comment first