Question 41 - PMI-RMP discussion
A project manager is developing the risk register and works with the team to analyze risks and determine their probability and impact. There is valuable historical data available that may be used to simulate the overall risk outcome.
Which type of analysis should the project manager use in this instance?
A.
Check list analysis
B.
Cause and effect
C.
Specialized meeting
D.
Quantitative analysis